The scheme also provides for deployment of 50 GWh of Battery Energy Storage Systems (BESS) at the Renewable Energy (RE) developer/generator end or any other location of importance for grid flexibility to address intermittency, congestion, peak-hour curtailment and meet non-solar hour demand.

GK and monthly revision
Cabinet approves Green Energy Corridor Phase-III scheme for Development of Intra-State Transmission System with Battery Energy Storage Systems
Digest date: . This is a dated report; check the source for subsequent developments.
The Union Cabinet chaired by the Prime Minister Shri Narendra Modi has approved the Green Energy Corridor Phase-III (GEC-III) scheme. This historic initiative will strengthen India’s Intra-State Transmission System (InSTS) to enable evacuation of up to 135 Gigawatt (GW) of renewable energy across States/ Union Territories.
Source: Press Information Bureau (official). The summary and key points above are extracts from that release. Any additional learning notes are labelled separately. Check the original report for the full text and later updates.
Key points
Exam-ready takeaways
The scheme is targeted to be set up by FY 2032-33 with total project outlay of Rs.1,86,405 crore, comprising Rs.1,36,378 crore for the development of Intra-State Transmission Systems (InSTS) under GEC-III, Rs.50,000 crore for 50 GWh of Battery Energy Storage Systems (BESS).
The Scheme involves a total Central Financial Support of Rs.54,082 crore.
The scheme will help in achieving the target of 900 GW installed Non-Fossil capacity by 2035.
Recall the report
Fill the missing fact
Try the gap before opening the answer. These exercises use the report’s own wording; they are practice prompts, not past exam questions.
The scheme is targeted to be set up by FY 2032-33 with total project outlay of Rs.[ … ], comprising Rs.1,36,378 crore for the development of Intra-State Transmission Systems (InSTS) under GEC-III, Rs.50,000 crore for 50 GWh of Battery Energy Storage Systems (BESS).
Reported answer: 1,86,405 crore
The scheme is targeted to be set up by FY 2032-33 with total project outlay of Rs.1,86,405 crore, comprising Rs.1,36,378 crore for the development of Intra-State Transmission Systems (InSTS) under GEC-III, Rs.50,000 crore for 50 GWh of Battery Energy Storage Systems (BESS).
The Scheme involves a total Central Financial Support of Rs.[ … ].
Reported answer: 54,082 crore
The Scheme involves a total Central Financial Support of Rs.54,082 crore.